6.59 km Tunnel-14 breakthrough on Rishikesh–Karanprayag rail line in Rudraprayag

6.59 किमी लंबी टनल-14 आर-पार, ऋषिकेश-कर्णप्रयाग रेल परियोजना को बड़ी कामयाबी
Computer-generated English audio

Rudraprayag: Rail Vikas Nigam Limited (RVNL) achieved the main breakthrough of the 6.59 km Tunnel-14 on the Rishikesh–Karanprayag rail project on 27 November 2026. The two sections of the tunnel, dug from Sumerpur and Marora, met inside the mountain in Rudraprayag district.

Rudraprayag is a hill district in the Garhwal region of the Himalayan state of Uttarakhand in northern India. The Rishikesh–Karanprayag line is a new railway being built through this mountainous terrain. RVNL is a public sector company under the Indian Railways that builds rail infrastructure.

WhatMain tunnel breakthrough of Tunnel-14
When27 November 2026
WhereRudraprayag district, Rishikesh–Karanprayag rail project
WhoRail Vikas Nigam Limited (RVNL)
Why-How4.7 km dug from Portal-1 (Sumerpur), 1.79 km from Portal-2 (Marora)

According to information shared by RVNL, 4.7 km of the tunnel was excavated from Portal-1 at Sumerpur and 1.79 km from Portal-2 at Marora. A portal is the entry point from which tunnelling starts. The two drives joined on 27 November.

Also read: Ex-Shinde Sena taluka chief Udaysingh Borade joins BJP in Mantha, made district VP

Digging through loose soil under homes

At Portal-1 (T14P1), engineers excavated a 110 m triple-track tunnel through loose soil beneath inhabited areas. Only 20–30 m of ground lay above the tunnel there. To do this safely, the team used pre-excavation and multi-drifting, a method in which the tunnel face is opened in several smaller sections instead of all at once.

At Portal-2 (T14P2), around 100 m was dug mechanically. Near both portals, controlled blasting was allowed only during the daytime, under strict rules, to protect nearby settlements.

Never miss a storyFollow News Nation Online on WhatsApp for breaking news from India and the world.
Follow on WhatsApp

Marora slope stabilised before main drive

RVNL said ground settlement at Marora and the acquisition of land and homes had to be resolved first. The slope at Portal-2 was then secured using 30–35 m deep micropiles, 15–20 m rock bolts and consolidation grouting, which strengthens weak ground by injecting grout into it. This allowed the main drive from that side to begin in March 2024.

For the 4.7 km drive from Portal-1, specialised ventilation systems supplied fresh air and regulated the temperature throughout the tunnel.

Photos from the site show a banner inside the tunnel carrying the name of Megha Engineering and Infrastructures Ltd and reading “Final Breakthrough Event of Tunnel 14 Main Tunnel Pkg-08”, dated 27.11.2026. Engineers and workers waved the Indian tricolour, and the tunnel mouth was decorated with balloons.

Key points

  • RVNL achieved the main breakthrough of the 6.59 km Tunnel-14 on 27 November 2026.
  • 4.7 km was dug from Sumerpur (Portal-1) and 1.79 km from Marora (Portal-2).
  • A 110 m triple-track stretch was dug through loose soil under inhabited areas, with 20–30 m of ground above it.
  • The Portal-2 slope was secured with micropiles, rock bolts and consolidation grouting. The main drive began in March 2024.
  • Controlled blasting near both portals was limited to daytime to protect settlements.

Read this story in Hindi: 6.59 किमी लंबी टनल-14 आर-पार, ऋषिकेश-कर्णप्रयाग रेल परियोजना को बड़ी कामयाबी

जालना, महाराष्ट्र और देश-दुनिया की ताज़ा खबरें
सीधे अपनी Facebook फ़ीड में पाएँ — News Nation Online पेज को Follow करें।
👍 Facebook पर Follow करें

Discover more from NewsNation Online

Subscribe to get the latest posts sent to your email.

आपके लिए सुझाव

author avatar
NewsNation Online Desk
The NewsNation Online Desk reports news from Jalna, Marathwada, Maharashtra, India and the world in Hindi, English, Marathi and Urdu. Stories are checked against official sources and published under our editorial standards.

Leave a Reply